Results 15
3.2.1.1 Mobile blasting inspections 15
Provision of company data 15
3.2.2.1 Operation, Management and Maintenance Plan 15
Results of receiving environment monitoring 16
page
ii
3.2.3.1 Deposition gauge monitoring 16
Discussion 16
Site performance and environmental effects 16
Evaluation of performance 17
Recommendations from the 2021-2022 Annual Report 19
Alterations to monitoring programmes for 2023-2024 19
Summary of performance for consent 10582-1 held by Technix Bitumen Technologies Ltd 25
List of figures
Figure 1 Port Taranaki log exports 2015 - 2022 4
Figure 2 Land use plan of Port Taranaki showing the location of the piped stormwater discharges and
the log yards (Revision April 2023) 5
Figure 3 Industries with separate resource consents operating within Port Taranaki, and location of
associated discharge sampling points 7
Figure 4 Port Taranaki industries compliance
constituents Inspections Yes
8. Limits on effects in receiving water Inspections/sampling Yes
9. Limits on effects from land
irrigation Inspections/sampling Yes
10. Provision of data Review of data Yes
11. Provision of a contingency plan Review of plan Yes
12. Provision of management plan Review of plan Yes
13. Notifications of changes in site
activity No changes this period N/A
14. Review of consent Next optional review in June 2026 N/A
Overall assessment of consent
Land Transport Plan 2024 for Public Consultation 25
9. Regional Speed Management Plan Update 203
10. Waka Kotahi Updates 213
11. Territorial Updates 239
12. Agenda Authorisation 256
Regional Transport Committee - Agenda
2
page
Whakataka te hau
Karakia to open and close meetings
Whakataka te hau ki te uru
Whakataka te hau ki tonga
Kia mākinakina ki uta
Kia mātaratara ki tai
Kia hī ake ana te atakura
He tio, he huka, he hauhu
Tūturu o
consents relating to the Eltham
landfill or provisions in Regional Plans.
Discussion
2.3.1 Discussion of site performance
The site has been closed for approximately 30 years and no incidents or complaints were logged by Council
during the year under review. The consent holder has a management and contingency plan in place for the
site.
2.3.2 Environmental effects of exercise of consents
In the past it has been difficult to accurately gauge the effects associated with the discharge of
due to a lack of
sand dune restoration is an ongoing concern. Improvements are required in the managing of the site, to
ensure this does not continue to degrade over time. The site management plan was updated to reflect this,
including planting plans.
For reference, in the 2022-2023 year, consent holders were found to achieve a high level of environment
performance and compliance for 878 (87%) of a total of 1007 consents monitored through the Taranaki
tailored monitoring programmes, while
• Lead the preparation of the monthly and annual financial reporting.
• Assist with preparation of forecasts, Annual Plan and Long-Term Plan
Budgets.
• Prepare and manage the process for financial reporting for the Taranaki
Stadium Trust.
Audit • Liaise with and lead the annual audit process.
Treasury • Lead the Treasury function and reporting, including debt management.
Finance systems • Assist with the development of finance and business systems and
practices.
Tax,
2022-2023 monitoring year however, STDC has indicated that there are plans in place for repairs to be
made over the 2023-2024 summer period which should mitigate these exceedances in future. There were no
other unauthorised incidents of non-compliance in respect of this consent holder during the period under
review.
For reference, in the 2022-2023 year, consent holders were found to achieve a high level of environmental
performance and compliance for 878 (87%) of a total of 1007 consents
need arise in the
future.
1.4.6 Assessment of data submitted by the Company
A significant component of the monitoring programme is the assessment of consent holder submitted data.
The Company is required to submit a wide range of data under the conditions of their DWI consents.
As required by the conditions of their consents, the Company has submitted an Injection Operation
Management Plan for each active injection well. The plans are required to include the operational details of
the
next report will be due in 2027.
Water take from the Waitara River
Methanex is required to supply Council with a report every two years addressing the programme Methanex
has in place to reduce their use of water. This report is a requirement of consent 0820-2 and 0801-2
(granted in April 2008). The most recent report was received in December 2022.
Contingency plans
Consent 3399-2 and 0822-2 both require the provision of a contingency plan by Methanex to the Council. It
is