sensor system, the Company can monitor the residual flows in the Manganui River, water levels in the
race and lake, and how much rain is falling locally. This has allowed the Company to manage race flows to
minimise flooding and has greatly improved the Company’s compliance with residual flow requirements.
Resource consents
The Company holds 13 resource consents, the details of which are summarised in the table below.
Summaries of the conditions attached to each permit are set out in Section
discharges treated water from the final aerobic pond
into the neighbouring Waiongana Stream in compliance with the conditions of Consent 0715-4.
page
5
Figure 1 Location of DH Lepper Trust piggery and Lepperton
1.3 Resource consents
Water abstraction permit
Section 14 of the RMA stipulates that no person may take, use, dam or divert any water, unless the activity is
expressly allowed for by a resource consent or a rule in a regional plan, or it falls within some
McIntyre
B K Raine
N W Walker
C S Williamson
Apologies
Notification of Late Items
Item Page Subject
Item 1 5 PowerCo Presentation to the Taranaki Regional Council -
PowerCo's 2018-2023 Investment Proposal
Item 2 19 Confirmation of Minutes
Item 3 26 Consents and Regulatory Committee Minutes
Item 4 32 Policy and Planning Committee Minutes
Item 5 38 Executive, Audit and Risk Committee Minutes
Item 6 44 Draft 2017/2018 Annual Plan - Statement of Proposal
2020
The fill area was coming to the end of fill capacity. No inappropriate material was observed. It was noted
that the first of the three silt fences needed to be repaired. Although it was fine during the inspection, it had
rained heavily prior to arrival, no issues were noted with regards to stormwater or visually in the receiving
water. No dust or odours were noted.
20 May 2021
No activity was occurring on the site during the inspection. There were some piles of soil at the top
be worse than it was due to rain earlier. The site manager advised this
would be cleaned up.
4 May 2022
The site was busy with normal operations. Traffic was particularly busy within the scrap area and some swarf
was observed tracking to the drains. All drain screens were in place and appear to be regularly maintained
to prevent blocking. All hazardous chemicals were appropriately contained. Rainwater within bunding was at
a low level. Spill kits were in place throughout the site and
NPDC NP wastewater treatment plant consent monitoring report - Taranaki Regional Council.
regional plan, or it falls within some particular
categories set out in Section 14.
The Company holds water permit 10247-1 to cover the abstraction of groundwater incidental to quarry
operations and for aggregate washing purposes. This permit was issued by the Council to the previous site
operators (Inglewood Metal Ltd) on 1 December 2016 under Section 87(d) of the RMA. The permit was then
transferred to The Company on 6 April 2017.
page
5
Figure 1 Quarry operations,
build a new
compressor onsite. The old flare pit had been tested for contamination prior to it being reinstated to
pasture. At the time of inspection no flare, heat haze or smoke was detected. The skimmer pits were visually
satisfactory. It was noted that the discharge pipe is kept closed during rain events to allow sediment to
settle out prior to discharge, with various tide marks around the pits showing that this was common
practice. Hydrocarbon cloth had been placed under the coil tubing
year
Standard hydrometric equipment $1,772.00 per year
Tangahoe hydrometric equipment $619.00 per year
Tawhiti hydrometric equipment (lower) $1,573.00 per year
Tawhiti hydrometric equipment (upper) $973.00 per year
Waingongoro hydrometric equipment $755.00 per year
Waitaha hydrometric equipment $7,356.00 per year
Rain Gauge Calibration $306.00 per deployment
Chlorine Meter $18.90 per use
Multi-parameter Field Meter $102.00 per day
EXPLANATION
This scale of charges is used to