stormwater and wastewater to
unnamed tributary of Mangahewa Stream 12/10/2011 2016 2031
7921-1 Discharge emissions to air 12/10/2011 2016 2031
7922-1 Water outlet structure installation and use 12/10/2011 2016 2031
1.3.1 Water abstraction permits
Section 14 of the RMA stipulates that no person may take, use, dam or divert any
water, unless the activity is expressly allowed for by a resource consent or a rule in a
regional plan, or it falls within some particular categories set
Beach Petroleum Kupe Production Station resource consent monitoring report 2019-2020
are working correctly.
Further plant upgrades were undertaken in the 2017-2018 season, as discussed in Section 2.1.
page
5
Photo 1 The Fonterra Whareroa site
1.3 Resource consents
1.3.1 Water abstraction permits
Section 14 of the RMA stipulates that no person may take, use, dam or divert any water, unless the activity is
expressly allowed for by a resource consent or a rule in a regional plan, or it falls within some particular
categories set out in Section
Mangahewa C hydraulic fracturing resource consent monitoring report 2018-2019
Waitaha catchment (Bell Block industrial) consent monitoring report 2019-2020
Kowhai D hydraulic fracturing resource consent monitoring report 2018-2020
Tawhiti Catchment Monitoring Annual Report 2020 2021
Freshwater physicochemical state of the environment monitoring report - Taranaki Regional Council.
STDC Waverley-Kaponga-Manaia-Patea oxidation ponds consent monitoring report - Taranaki Regional Council.
stormwater drain at the Maui Production Station, April 2013
There were eight instances of low levels of glycol being detected in the Company’s
daily combined stormwater discharge samples during the period under review. The
highest concentration was recorded on 21 June 2015 after approximately 100 mm of
rain fell in the preceding days and caused residual glycol in process area drains to
wash into the stormwater system and through the outfall. No adverse environmental
effects were recorded as a