the
time of the inspection with 5 mm of rain over the past three days.
Significant earthworks were being undertaken at the site. The contractor on-site
outlined that the whole area was being prepared for eventual filling. Pipe had been laid
down the length of both channels to pipe the spring water. Stormwater pipes and risers
had also been installed to intercept stormwater from the surrounding pasture. At the
time of the inspection, the contractor was digging a retention/silt pond for
this area.
The truck wash area looked to be working well. The settling ponds at the truck wash
area were full with a small clear discharge to the drain. There was some evidence of
fines in the drain due to recent rain and the pump having broken down which was
being repaired. The slurry area at the back of the yard was full which would need to
be emptied soon. The main drain through the yard had been cleaned out. Overall the
site looked to be well maintained and managed at the time of
tidy.
31 January 2012
The site was unmanned at the time of inspection. There was processing equipment
onsite. The hill that had been pushed into the quarry pit for reinstatement had been
graded and contoured. There was no dust found beyond the boundary of the property.
There was no runoff from the site occurring at the time of inspection. The site was tidy.
14 May 2012
The site was unmanned at the time of inspection. It was raining and windy at the time
of inspection. The reinstated
Regional Transport Committee Agenda March 2025
Ltd
(For a copy of the signed resource consent
please contact the TRC Consents department)
page
Water abstraction permits
Section 14 of the RMA stipulates that no person may take, use, dam or divert any water, unless the activity is
expressly allowed for by a resource consent or a rule in a regional plan, or it falls within some particular
categories set out in Section 14. Permits authorising the abstraction of water are issued by the Council
under Section
rule in a regional plan, or by national
regulations. Methanex currently holds a consent for a flood control structure in the
Waitara River.
Section 14 of the RMA stipulates that no person may take, use, dam or divert any
water, unless the activity is expressly allowed for by a resource consent or a rule in a
regional plan, or it falls within some particular categories set out in Section 14.
Methanex currently holds two abstraction consents for the Waitara River.
page
Operations and Regulatory Agenda 30 April 2024
Climate change projections and impacts for Taranaki May 2022
… levels are $8m per annum over the ten years of the 2021/2031 Long-Term Plan.
Dividends are a significant portion of the Council’s revenue streams. Port Taranaki Ltd operates in a highly-competitive
trading environment and there are no guarantees that it will be able to continue to deliver forecast dividend levels.
Accordingly there is a risk that profits and dividends may fall at some future point. This is the biggest risk to the delivery
of the proposed programmes.
Over the 10
Westside Corporation Pty Ltd Deep Well Injection Annual Report 2023 2024