the Manganui River, water levels in the
race and lake, and how much rain is falling locally. This has allowed the Company to manage race flows to
minimise flooding, and has greatly improved the Company’s compliance with residual flow requirements.
Resource consents
The Company holds 13 resource consents, the details of which are summarised in the table below.
Summaries of the conditions attached to each permit are set out in Section 3 of this report.
A summary of the various consent
included in this memorandum has been
prepared in accordance with generally accepted accounting practice.
26. Design costs of $5,215.25 (incl GST) have been absorbed into the existing TEMO budget.
27. Printing costs will need to be considered for the adopted Group Plan and the number of physical
copies to print. This is likely to fall into the financial year 2025/26.
Civil Defence Emergency Management - Joint Committee - Draft Taranaki Civil Defence Emergency Management Group Plan
Nitrogen also enters the Irrigation Area with rain and clover fixation.
4.4 Total volume of irrigation liquid irrigated onto the Irrigation Blocks
The irrigation liquid is pumped from the pond to the irrigator through a buried pipeline. The pumping flow rate
was measured by BTW company in 2015 as 30 m3/hr1.
1 Uruti Composting Facility Management Plan, BTW Company Limited, 2015. (provided as Appendix J of the Application for
Consent Renewal)
page
11
Irrigation Block
page
Doc# 2197366-v1
Minutes of the Policy and Planning
Committee Meeting of the Taranaki
Regional Council, held in the Taranaki
Regional Council Chambers, 47 Cloten
Road, Stratford, on Tuesday 5 February
2019 at 10.35am.
Members Councillors N W Walker (Committee Chairperson)
M P Joyce
C L Littlewood
D H McIntyre
B K Raine
C S Williamson
D N MacLeod (ex officio)
Representative Councillor G Boyde (Stratford District Council)
Members Mr J
page
Doc# 2100506-v1
Minutes of the Ordinary Meeting of the
Taranaki Regional Council, held
Taranaki Regional Council Chambers, 47
Cloten Road, Stratford, on Tuesday 7
August 2018 at 10.40am.
Present Councillors D N MacLeod (Chairperson)
M J Cloke
D L Lean (Deputy Chairperson)
C L Littlewood
D H McIntyre
B K Raine
N W Walker
C S Williamson
Attending Messrs B G Chamberlain (Chief Executive)
A D McLay
Taranaki climate hazards & extremes - high winds & tornadoes (NIWA, 2007).
values are not readily obtainable are not recognised. For an asset to be sold, the asset is impaired if the market price for an equivalent asset falls below its carrying amount. For an asset to be used by the Trust, the asset is impaired if the value to the Trust in using the asset falls below the carrying amount of the asset.
Work in progress is recorded at cost. Cost includes expenditure which is directly attributable to the acquisition of an asset. Capital work in progress is not
Policy and Planning Agenda September 2024
Councillor B K Raine
Councillor C S Williamson
Councillor D L Lean (ex officio)
Councillor D N MacLeod (ex officio)
Representative Ms E Bailey (Iwi Representative)
Members Councillor G Boyde (Stratford District Council)
Mr J Hooker (Iwi Representative)
Councillor R Jordan (New Plymouth District Council)
Mr P Muir (Taranaki Federated Farmers)
Councillor P Nixon (South Taranaki District Council)
Mr M Ritai (Iwi Representative)
Apologies
Notification of Late Items
5350-1 To dam and divert water
5351-1
To erect, place and maintain structures in the beds of the
unnamed tributaries
The permits are discussed further in sections 1.3.1 to 1.3.5 below, with copies attached
to this report in Appendix 1.
1.3.1 Water permit
Section 14 of the RMA stipulates that no person may take, use, dam or divert any
water, unless the activity is expressly allowed for by a resource consent or a rule in a
regional plan, or it falls within some particular