transfer the sales gas from the
production station to the Kapuni Gas Treatment Plant.
1.3 Resource consents
1.3.1 Water abstraction permit
Section 14 of the RMA stipulates that no person may take, use, dam or divert any
water, unless the activity is expressly allowed for by a resource consent or a rule in a
regional plan, or it falls within some particular categories set out in Section 14.
Permits 6540 and 6541 to take and use groundwater from a bore/s lapsed in June 2010
and have
Annual Report 2012/2013 - full document.
that no person may take, use, dam or divert any
water, unless the activity is expressly allowed for by a resource consent or a rule in a
regional plan, or it falls within some particular categories set out in Section 14.
Fonterra holds water permit 0047 to cover the abstraction of water from the Tawhiti
Stream (Photograph 2), a tributary of the Tangahoe River, for the processing and
manufacture of dairy products, cleaning of plant, and cooling purposes. This permit
page
Contact Energy Stratford Power Station consent monitoring report 2019-2020
Fonterra Whareroa Annual Report 2020-2021
Section 14 of the RMA stipulates that no person may take, use, dam or divert any water, unless the activity is
expressly allowed for by a resource consent or a rule in a regional plan, or it falls within some particular
categories set out in Section 14.
Beach Energy holds water permit 7010-1 to take and use up to 3,500 m3/day groundwater at a maximum
rate of 40 L/s as a combined total from up to seven water bores in a bore field for the purpose of horizontal
directional drilling, pipeline
transfer the sales gas from the production station to the Kapuni Gas Treatment
Plant.
Figure 2 Components of the Kupe Gas Project
Note: Figure 2 sourced from: http://www.originenergy.com.au/1222/Kupe-Gas-Project
1.3 Resource consents
1.3.1 Water abstraction permit
Section 14 of the RMA stipulates that no person may take, use, dam or divert any water, unless the activity is
expressly allowed for by a resource consent or a rule in a regional plan, or it falls within some particular
to discharge water.
See table 1 and 2 for a summary of the resource consents issued in relation to quarry operations in
Taranaki.
1.2.2. Water abstraction permits
Section 14 of the RMA stipulates that no person may take, use, dam or divert any water, unless the activity
is expressly allowed for by a resource consent or a rule in a regional plan, or it falls within some particular
categories set out in Section 14.
There are seven monitored quarries in Taranaki that hold a water
1.3.1 Water abstraction permit
Section 14 of the RMA stipulates that no person may take, use, dam or divert any
water, unless the activity is expressly allowed for by a resource consent or a rule in a
regional plan, or it falls within some particular categories set out in Section 14.
Origin Energy holds water permit 7010-1 to take and use up to 3,500 m3/day
groundwater at a maximum rate of 40 l/s as a combined total from up to seven water
bores in a bore field for the purpose of