allowed for by a resource consent or a rule in a regional plan, or it falls within some particular
categories set out in Section 14. Permits authorising the abstraction of water are issued by the Council
under Section 87(d) of the RMA.
Water discharge permits
Section 15(1)(a) of the RMA stipulates that no person may discharge any contaminant into water, unless the
activity is expressly allowed for by a resource consent or a rule in a regional plan, or by national regulations.
Permits
Consents department)
page
Water abstraction permits
Section 14 of the RMA stipulates that no person may take, use, dam or divert any water, unless the activity is
expressly allowed for by a resource consent or a rule in a regional plan, or it falls within some particular
categories set out in Section 14. Permits authorising the abstraction of water are issued by the Council
under Section 87(d) of the RMA.
Water discharge permits
Section 15(1)(a) of the RMA
consents held by
Oaonui Water Supply Ltd
(For a copy of the signed resource consent
please contact the TRC Consents department)
page
Water abstraction permits
Section 14 of the RMA stipulates that no person may take, use, dam or divert any water, unless the activity is
expressly allowed for by a resource consent or a rule in a regional plan, or it falls within some particular
categories set out in Section 14. Permits authorising the abstraction of water are
a large pond. The outlet from the pond is an inverted pipe located at the
opposite end of the pond from the inlet. The discharge from the pond emerges from a pipe to fall over a
small waterfall. At the base of the waterfall the discharged water runs down a natural cobbled channel
beneath native riparian vegetation for approximately 10 metres before entering the Patea River,
downstream of the intake weir.
1.2.2 Midhirst water supply
The Midhirst community WTP was originally supplied the
Puketapu for a land-based
disposal (as w ell as suggesting that airport land be used for that purpose). We w ere
told that such use aligns w ith the fact that portions of the land are already used for the
disposal of solid w aste from the NP WWTP. Such an offer is generous, but Mr Kitto
advised us that at most there w as 311 hectares of land available at Puketapu and it
was some 7 km distant from the New Plymouth WWTP. The land in question falls far
short of the requirements identif ied by Mr Manning.
high water springs, the
application falls under Rule C1.8 “Erection or placement of a large structure or
structures, and related occupation of the coastal marine area” and is classified as a
discretionary and restricted coastal activity. As such, the Minister of Conservation is the
consent authority for this application.
3. The application was received on 26 October 2006, accompanied by an assessment of
environmental effects [AEE] prepared by the applicant’s consultant, MWH NZ Ltd
Flexgas Ltd Ahuroa B Gas Storage Facility Annual Report 2022-2023
Osflo Fertiliser Ltd Monitoring Programme Annual Report 2021-2022
2019-13.
page
Appendix I
Resource consents held by
Westown Haulage Ltd
(For a copy of the signed resource consent
please contact the TRC Consents department)
page
Water abstraction permits
Section 14 of the RMA stipulates that no person may take, use, dam or divert any water, unless the activity is
expressly allowed for by a resource consent or a rule in a regional plan, or it falls within some particular …
page
Policy and Planning Committee
Tuesday 25 July 2017
10.30am
Taranaki Regional Council, Stratford
page
Agenda for the meeting of the Policy and Planning Committee to be held in the
Taranaki Regional Council chambers, 47 Cloten Road, Stratford, on Tuesday 25
July 2017 commencing at 10.30am.
Members Councillor N W Walker (Committee Chairperson)
Councillor C L Littlewood
Councillor D H McIntyre
Councillor B K Raine
Councillor D