Your search for 'rain fall' returned 1967 results.

Kintyre Bush; Raurimu

regenerating well. Drains running North to south on both the eastern and western boundaries will also be altering the hydrology of the site. Herbivores - Medium Stock are excluded from the site through drains and a two wire fence around the perimeter. Stock incursions are infrequent. Possum Self-help This site falls within the Opunake possum self-help operation. Leg- hold trapping is carried out annually by a contractor. Predators - Medium Predators including rodents, mustelids, possums,

Value Timber monitoring report 2017-2018

well-maintained with approximately ten small stockpiles of sawdust waiting to be spread. The area was intact, with no cracking or slumping evident on either the fill area or the tip face. No unauthorised material was noted. There was no ponding observed, despite heavy rain the previous day, and the material was damp underfoot. The pre-fill gully was well grassed with no sign of exposed soil or sediment runoff. The stage 1 fill area was damp underfoot and had been recently grazed, and showed no sign of

Annual report 2015-2016

minor amount of erosion at one point that was likely to have been caused by the heavy rain in the previous week. The stormwater ponds were all nearly full, with approximately 0.3-0.5 m of freeboard. The contents were a relatively clear brown colour, and the lowest pond had an iron oxide sheen present on the surface. The downstream stormwater drain had recently been cleared of vegetation and there were no obstructions to flow. Silt controls were in place, and appeared to be effective as the

Biennial report 2011-2013

tidy. 31 January 2012 The site was unmanned at the time of inspection. There was processing equipment onsite. The hill that had been pushed into the quarry pit for reinstatement had been graded and contoured. There was no dust found beyond the boundary of the property. There was no runoff from the site occurring at the time of inspection. The site was tidy. 14 May 2012 The site was unmanned at the time of inspection. It was raining and windy at the time of inspection. The reinstated

Annual report 2013-2014

the time of the inspection with 5 mm of rain over the past three days. Significant earthworks were being undertaken at the site. The contractor on-site outlined that the whole area was being prepared for eventual filling. Pipe had been laid down the length of both channels to pipe the spring water. Stormwater pipes and risers had also been installed to intercept stormwater from the surrounding pasture. At the time of the inspection, the contractor was digging a retention/silt pond for

Annual report 2013-2014

this area. The truck wash area looked to be working well. The settling ponds at the truck wash area were full with a small clear discharge to the drain. There was some evidence of fines in the drain due to recent rain and the pump having broken down which was being repaired. The slurry area at the back of the yard was full which would need to be emptied soon. The main drain through the yard had been cleaned out. Overall the site looked to be well maintained and managed at the time of

Public notice - final representation arrangements

considerations justify otherwise. The representation of the Stratford and South Taranaki constituencies falls outside the stipulated range. The Council considers that the Stratford Constituency warrants one member and the South Taranaki Constituency warrants three members for the following reasons: • the proposed representation reflects the status quo (with only minor proposed boundary changes), which is well understood and accepted by the regional community. • the constituency boundaries are

Long-Term Plan 2021/2031

… levels are $8m per annum over the ten years of the 2021/2031 Long-Term Plan. Dividends are a significant portion of the Council’s revenue streams. Port Taranaki Ltd operates in a highly-competitive trading environment and there are no guarantees that it will be able to continue to deliver forecast dividend levels. Accordingly there is a risk that profits and dividends may fall at some future point. This is the biggest risk to the delivery of the proposed programmes. Over the 10

2021/2022 schedules of charges

… hydrometric equipment (upper) $973.00 per year Waingongoro hydrometric equipment $755.00 per year Waitaha hydrometric equipment $7,356.00 per year Rain Gauge Calibration $306.00 per deployment Chlorine Meter $18.90 per use Multi-parameter Field Meter $102.00 per day EXPLANATION This scale of charges is used to calculate the Council's actual and reasonable costs when carrying out functions under the Resource Management Act 1991. Where those actual and reasonable costs exceed any specified