the same level of protection to
instream fauna across the full range of river/stream sizes. Following discussions with iwi and the Wai
Maori Group post the publication of the 2019 report, it was agreed that additional work was
required to test these assumptions in both small streams and large rivers.
Instream habitat surveys were initially carried out at sites on 12 Taranaki streams and rivers
(Kapoaiaia, Kaupokonui, Manganui, Mangaoraka, Patea, Tangahoe, Waingongoro (2 sites),
Quarterly Operational Report December 2020
Quarterly Operational Report March 2021
Wai-iti Beach Retreat monitoring report 2018-2019
Quarterly operational report September 2015.
Agenda for Hearing of submissions on Proposed Pest Management Plan & Draft Biosecurity Strategy October 2017.
Ballance Kapuni consent monitoring 2020-2021
Quarterly Operational Report September 2020
to provide a technology report on two
occasions, while Condition 20 requires an annual report. Condition 21 states that the
consent holder must maintain a contingency plan for the site.
Conditions 22 and 23 require the consent holder to meet with Council, iwi and
interested parties regarding the operation and monitoring of the consent.
Condition 24 is a review provision.
NPDC holds discharge permit 2982-4 to cover the discharge of up to 60 m3/day of
leachate from a sludge