for the period July 2014-June 2015
describes the monitoring programme implemented by the Taranaki Regional Council (the
Council) to assess Trustpower’s environmental performance during the period under review,
and the results and environmental effects of their activities.
Trustpower holds a total of 23 resource consents, which include a total of 186 conditions
setting out the requirements that the Company must satisfy. The Company holds five consents
to allow it to take and use water, five
Otaraoa Road at Motunui in the Waipapa and Manu catchments. This report for the
period July 2017 to June 2018 describes the monitoring programme implemented by the Taranaki Regional
Council (the Council) to assess the Company’s environmental and consent compliance performance during
the period under review. The report also details the results of the monitoring undertaken and assesses the
environmental effects of the Company’s activities.
The Company holds 17 resource consents, which include a
operates a petrochemical production
station located on Inaha Road at Manaia, in the Inaha catchment. The Kupe Production Station
processes oil and gas from the offshore Kupe wells. This report for the period July 2014–June
2015 describes the monitoring programme implemented by the Taranaki Regional Council (the
Council) to assess the Company’s environmental performance during the period under
review, and the results and environmental effects of the Company’s activities.
The Company holds 15
the Waitotara catchment. This report, for the period 1 October 2017 to 30 September 2018
coincides with killing season, it describes the monitoring programme implemented by the Taranaki Regional
Council (the Council) to assess the Company’s environmental and consent compliance performance during
the period under review. The report also details the results of the monitoring undertaken and assesses the
environmental effects of the Company’s activities.
The Company holds a total of five
(WWTP) located to the west of Opunake in the Heimama catchment. This
report for the period July 2015 to June 2016 describes the monitoring programme implemented
by the Taranaki Regional Council (the Council) to assess STDC’s environmental performance
during the period under review. The report also details the results of the monitoring
undertaken and assesses the environmental effects of the Company’s activities.
STDC holds three resource consents, which include a total of 32 conditions setting
District Council (STDC) holds consents to cover the discharge of leachate and
stormwater from seven closed landfills. The landfills are at Kaponga and Manaia in the Waiokura catchment,
Patea in the Patea catchment, Opunake in the Otahi catchment, Hawera in the Tangahoe catchment,
Otakeho in the Taikatu catchment and Eltham in the Waingongoro catchment.
This report for the period July 2016 to June 2017 describes the monitoring programmes implemented by
the Taranaki Regional Council (the Council)
operates two quarries in Taranaki. One is located off York Road in
the Waitara catchment; and the other is located off Toko Road in the Patea catchment. Both
operate on a commercial basis.
This report for the period July 2012-June 2013 describes the monitoring programme
implemented by the Taranaki Regional Council to assess the Company’s environmental
performance and environmental effects of the Company’s activities.
Vickers Quarries Ltd holds a total of four resource consents to cover
24-05412-3.1 R2/5412-3.1 New Plymouth District Council 10-Jun-24 Change of consent conditions
To occupy the Coastal Marine Area with a boulder rip rap minor toe
protection and a stormwater outlet for coastal erosion control
purposes...change of conditions Coastal Permit 107 Messenger Terrace, Oakura Oakura
24-11257-1.1 R2/11257-1.1 Nick Loveridge-Easther 10-Jun-24 Change of consent conditions
To occupy the Coastal Marine Area with a boulder rip rap minor toe
protection and a stormwater outlet
discharge of laboratory waste
and unprocessable wastes to waste pits; the discharge of dairy liquids to land and the
discharge of emissions to air. This report for the period July 2014 to June 2015 describes the
monitoring programme implemented by the Taranaki Regional Council (the Council) to
assess Fonterra’s environmental performance during the period under review, and the
results and environmental effects of their activities.
Fonterra holds a total of 26 resource consents, which include
photos
Photo 1 Stormwater erosion in south eastern area of the site 6 December 2018 6
page
1
1 Introduction
1.1 Compliance monitoring programme reports and the Resource
Management Act 1991
1.1.1 Introduction
This report is for the period July 2018 to June 2019 by the Taranaki Regional Council (the Council) on the
monitoring programme associated with the resource consent held by South Taranaki District Council (STDC).
STDC operates a greenwaste disposal