2 Results
2.1 Inspections
30 July 2019
An inspection was undertaken under consent 5838-2.2 (this is the discharge to land consent) as part of
routine compliance monitoring. The inspection was carried out in fine weather conditions following rain
within the previous 24 hours. The surface water bodies across the site were elevated, swift and turbid.
An inspection of the site found that the irrigation areas were wet with standing water observed on the
uppermost irrigation area. …
stock. There were issues around keeping buried
product in the ground due to elevated groundwater levels, the officer noted that the pits appeared to be
well managed. At the time of the inspection a discharge pipe to pond 1 had been damaged and product is
leaking into the ground. TBP was advised that this needed to be resolved before the next inspection.
4 May 2022
At the time of the inspection, the inspecting officer was advised that heavy rain had contributed to high
groundwater levels
“customer site” for
a. A minimum of 3 weeks, before spreading (no turning
required).
page
Remediation (NZ) Ltd RW-P-751-001-B
Organic Production Protocols Greenwaste Composting & Vermiculture
- 8 -
b. A cover should be applied to reduce excess moisture
retention from rain events.
c. The Revital contract spreader will ensure that before the
product is spread it has met 2(a) above, and the spreading
records will be filed as part of the
climate, central
government reforms and our evolving relationship
with tangata whenua.
While inflation has been trending down and is now
falling close to the Reserve Bank of New Zealand’s
target consumer inflation rate of between 1 and 3
per cent, the economy has remained sluggish with
gross domestic product rising by just 0.2% in the
March 2024 quarter. That followed a 0.1% fall in the
previous quarter.
We’ve had to factor these economic headwinds as
we
growth of multiple species and approaching acute
impact level for sensitive species at higher concentrations).
The national bottom line sits between bands B and C.
For nitrate, all 15 sites monitored in Taranaki achieved
national bottom lines, with all but three falling in band A
for both the annual median and 95th percentile measures.
The sites in band B were in mid and lower parts of southern
ring plain catchments, which are areas of more intensive
pastoral
When compared to criteria set out in the National Objectives
Framework (NOF), Lake Rotorangi falls within band B for
TLI Score Description Classification
0 - 2
Microtrophic: The lake is very clean with very low levels of nutrients and algae. The
lake can have snow or glacial sources.
Very good
>2 - 3 Oligotrophic: The lake is clear and blue, with low levels of nutrients and algae Good
>3 - 4 Mesotrophic: The lake has moderate levels of nutrients and algae. Fair
>4 - 5
using a correlation between these two sites, a calculated flow
can be estimated for the ‘Bushline. Based on this correlation, as shown in Figure 4 the flow did not fall below
the 134L/s limit, so no restrictions were required to be put in place.
Aug-2023 Oct-2023 Dec-2023 Feb-2024 Apr-2024 Jun-2024
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
5.0
5.5
6.0
6.5
7.0
7.5
8.0
8.5
9.0
9.5
10.0
10.5
11.0
11.5
12.0
12.5
13.0
geographic information system. These layers may be used to assist in developing
maps showing evacuation areas, in accordance with the Ministry of Civil Defence and
Emergency Management guidelines.
2 Method of Analysis
A typical tsunami wave analysis usually includes a method of generating the offshore
waves using a model which simulates underground movement of the earth (an
earthquake or underwater landslide), which then causes the rapid rise or fall of the
water surface, which then
that there may be other chances for Transport Choices funding and Public
Transport opportunities.
• Inflation has had a large impact, with cut backs in place to ensure rate payers are
not having to pay extra. Low cost low risk programmes have been deferred.
• The coastal walkway extension has had all Iwi informed with handover to follow
soon.
• An incident occurred involving a tree falling in Ōakura, resulted in NPDC being
found liable for the damage due to the tree’s position and
Change team are creating an
action plan to target reduction of key waste streams, system improvements,
and education.
Figure 1 Sorted waste from the NPDC Civic Centre Waste Audit
NPDC Zero Waste Fund – latest funding round
9. NPDC runs a Zero Waste Fund for community initiatives that will minimise
waste. The current round is open for applications from 1 October to 31 October
2024. Priority for this funding round will be given to those projects that fall in
the upper two levels of