Your search for 'rain fall' returned 1977 results.

Annual report 2014-2015

remediation pad. Any rain run-off and leachate that is generated, drains into a series of ponds for treatment. Between each pond there is a baffle that skims off any floating hydrocarbons as the leachate passes through. These ponds also treat the leachate and stormwater from pad 1 where remediated drilling wastes are stored and/or processed further. The treated liquid from the pond treatment system (PTS) is then irrigated to cut and carry pasture on two irrigation areas. Run off and leachate

Consents and Regulatory Committee Agenda March 2022

104A of the Resource Management Act). Rules 35 and 36 of the RFWP do not include any matters of control that expressly allow for the consideration of matters such as those expressed in the NPS-FM objective. Given that the Council can only consider policies that relate to the matters over which the Council has reserved control through the plan itself, the Council is unable to take into account matters that fall outside this scope. R2/10979-1.0 Commencement Date:

STDC Waiinu Beach Settlement Annual Report 2021-2022

Site inspections 17 December 2021 - The camp was quiet at the time of inspection with only one bus, one motorhome and two caravans in residence. The STDC officer noted that the holding tanks had been full as a result of heavy rain but had reduced the following day. While there have been odour complaints in the past, at the time of inspection there were no odours or visual issues near the WWTP or trenches. The sea was a turbid brown at the time, and there had been lots of rain preceding the

North Taranaki kaimoana survey 2000-2001

sea, but these are generally few in number and only the rare spills have a major and indeed measurable impact on seafoods in the area. “Indirect” discharges is a term used to generally describe the effects of rivers on the coast, and therefore include the considerable amounts of faecal bacteria, nutrients and solids carried down the Waitara River after rain on the farms and hill country upstream (now seen as the major source of these in local seafoods). The material and

Mangati Catchment Joint Monitoring Programme Annual Report 2020 2021

is approximately 6.1 km2. The length of the catchment, from the headwaters between Paraite and Corbett Roads to the sea at Bell Block beach, is approximately five kilometres. The industrial area at Bell Block is situated mid-catchment (Figure 1). Historically, the industrial areas were located predominantly on the western side of the stream however ongoing development since 2016 has resulted in more sites on the eastern side. These sites fall under permitted activity rules and are not

Central Greenwaste & Firewood consent monitoring 2018-2020

the contained area or soak hole, even in the heavy rain occurring at the time of inspection. Overall the site looked tidy and appeared to be well managed at the time of inspection. 21 February 2019 The site has had a few new loads of green waste placed on it. There was no evidence of any stormwater or leachate discharge on site and there was nothing collected in the contained corner of the site. Overall the site was being managed in an appropriate manner at the time of inspection. …

Water metering and reporting

installed as per manufacturer's specifications or as outlined in the Water Measurement Code of Practice. You must provide an installation certificate to the Council following any new installation. Verification of water metersFor measuring and reporting to be useful, we must be able to rely confidently on the water-take data we get. All water meters that fall under the national regulations or under resource consent requirement must be verified to be accurate to within ± 5%. Verification is required

Water metering and reporting

installed as per manufacturer's specifications or as outlined in the Water Measurement Code of Practice. You must provide an installation certificate to the Council following any new installation. Verification of water metersFor measuring and reporting to be useful, we must be able to rely confidently on the water-take data we get. All water meters that fall under the national regulations or under resource consent requirement must be verified to be accurate to within ± 5%. Verification is required

Annual report 2012-2013

sites were inspected on three occasions during the monitoring year. A summary of the notes made during these inspections is given below. 2.1.1 9 August 2012 A site visit was made to conduct a compliance monitoring inspection. It was raining at the time of the inspection with 14 mm falling over the past 72 hours. A meeting was held at the site office with the director of the Company to discuss the new consents. The requirement to provide management plans was also discussed. Monk