Demolition to start on Yarrow Stadium East Stand

Mon 29 Mar 2021
Demolition of Yarrow Stadium’s East Stand is scheduled to start mid-April and will be finished by September, the Taranaki Regional Council announced today.
Read moreMon 29 Mar 2021
Demolition of Yarrow Stadium’s East Stand is scheduled to start mid-April and will be finished by September, the Taranaki Regional Council announced today.
Read moreThu 25 Feb 2021
Clearer timelines are emerging as good progress is made in the Yarrow Stadium Redevelopment Project. West Stand repairs are expected to be finished in November, with sporting and other events possible at the venue next year.
Read moreMon 07 Dec 2020
New Plymouth-based Clelands Construction has won the contract to repair the West Stand at Yarrow Stadium, with work beginning almost immediately.
Read moreTue 03 Nov 2020
Yarrow Stadium will be remodelled to suit a broader range of regional and community sports while continuing to be the premier regional venue for top-level sport in the post-COVID era.
Read moreTue 11 Aug 2020
Work is resuming on the repair and refurbishment of Yarrow Stadium, as a $20 million ‘shovel-ready’ funding injection for the project is formally accepted by the Taranaki Regional Council on behalf of the community.
Read moreThu 23 Jul 2020 1:00pm
Today’s $20 million Government injection for Yarrow Stadium is great news for ratepayers and will allow the iconic venue to be back in operation as soon as possible, says the Taranaki Regional Council.
Read moreFri 27 Mar 2020
The Taranaki Regional Council will not call for tenders for the repair and refurbishment of Yarrow Stadium until there is greater clarity on the impacts of the Covid-19 pandemic.
Read moreWed 11 Mar 2020
Fifteen potential contractors have expressed interest in the Taranaki Regional Council’s Yarrow Stadium repair and refurbishment project.
Read more